Resource histogram by weeks.

I'm doing something wrong. I can't get my resource histogram to display by week. It sums to month. Help.

[[wysiwyg_imageupload:2382:]]

D
Dennis Hanks 👤 Member for 19 years 1 month

Tom;

The issue is ordinal dates. The workaround is a small pain - moving back and forth from Timescale Date Format changing in Primary Dates applying, changing again in Primary Dates and re-applying. Apparently the 'bug' has been around since P5. Not a high priority for Larry. Attached is what it should like. Thanks for trying.

[[wysiwyg_imageupload:2391:]]

R
Raymund de Laza 👤 Member for 16 years 6 months

Dennis,

In User Prefrences.. Resource Analysis.. Set Interval into weeks...

 

Regards,

T
Tom Turnham 👤 Member for 12 years 9 months

Strange. Im affraid I cant help.... When I change the timescale it amends the bars to suit

[[wysiwyg_imageupload:2390:]]

D
Dennis Hanks 👤 Member for 19 years 1 month

Tom;

Thanks for the response. Apparently the screen shot is not opening. I'll post again. It should show the timescale set at weeks for schedule and histogram, yet resources are grouped by month. I've sent a Service Request to Oracle - no response. Posting jpg now.

[[wysiwyg_imageupload:2389:]]

T
Tom Turnham 👤 Member for 12 years 9 months

Are you just showing it at the buttom of the window using the 'Resource Usage Profile'?

If so just right click in the right hand side of the window and select 'Timescale'. You can then chose the appropriate timescale (Month/Week)

If you are copying it into Excel then go to the 'Assignments' window and do the same (right click in the right window and select 'Timescale')

 

P.S a little courtesy goes a long way.

Forum Sponsor

Top Posters

Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts