Painting
Task / DescriptionSlow Ave Fast Units Prepare Walls- 14.2 - m2/hr Prepare Doors- 12.5 - m2/hr Prepare Door Frames- 25.0 - m/hr Burn Off / Heat Strip Paintwork- 1.1 - m2/hr Internal Timber, 1 coat primer before fixing, generally- 6.7 - m2/hr Internal Timber, 1 coat primer before fixing, timber lengths- 20.0 - m/hr Internal Timber, knot, 1 primer, stop, 1 undercoat, 1 gloss- 1.7 2.1 m2/hr Internal Timber, touchup primer, 1 undercoat, 1 coat gloss- 3.1 3.8 m2/hr Internal Timber, polyurethane varnish, 2 coats- 3.3 - m2/hr Internal Timber, polyurethane varnish, 3 coats- 2.2 - m2/hr Internal Timber, linseed oil to hardwood, 2 coats- 3.6 - m2/hr External Timber, windows and frames- 2.4 - m2/hr External Timber, knot, 1 primer, 2 undercoats, 1 coat gloss,- 1.5 - m2/hr External Timber, touchup primer, 2 undercoats, 1 coat gloss,- 2.0 - m2/hr External Timber, 2 coats wood preservative- 4.0 - m2/hr External Timber, 3 coats polyurethane varnish- 2.0 - m2/hr Internal Walls, 2 coats emulsion to plaster- 8.0 - m2/hr Internal Walls, 2 coats emulsion to brick/blockwork- 6.0 - m2/hr Internal Walls, 1 mist, 2 coats emulsion to plaster- 6.0 - m2/hr Internal Walls, 1 mist, 2 coats emulsion to brick/blockwork- 4.5 - m2/hr Internal Walls, 1 primer, 1 undercoat, 1 gloss to plaster- 2.3 - m2/hr Internal Walls, undercoat to door frame- 20.0 - m/hr Internal Walls, gloss to door frame- 16.5 - m/hr Internal Walls, undercoat to door- 7.1 - m2/hr Internal Walls, gloss to door- 6.2 - m2/hr External Walls, 2 coats sandtex to render/concrete- 2.5 - m2/hr External Walls, 2 coats sandtex to brick/blockwork- 2.0 - m2/hr External Walls, 1 sealer, 2 emulsion to render/concrete- 2.0 - m2/hr External Walls, 1 sealer, 2 emulsion to brick/blockwork- 1.7 - m2/hr Floors, epoxy paint- 2.9 - m2/hr Ceilings, emulsion paint, 2 coats- 6.1 - m2/hr Ceilings, emulsion paint, 3 coats- 5.0 - m2/hr Ceilings, textured paint- 4.2 - m2/hr Ceilings, artex finish- 4.1 - m2/hr Internal Steelwork, 1 primer, 1 undercoat, 1 gloss1.3 2.4 - m2/hr External Steelwork, 1 primer, 2 undercoats, 1 gloss0.9 1.7 - m2/hr Guttering Steelwork, 1 coat primer, 2 undercoats, 1 gloss- 2.5 - m/hr
Book navigation for Painting & Decorations
-
-
-
-
-
-
-
-
-
-
-
Painting & Decorations
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-