Barrette Piles
Task / DescriptionSlow Ave Fast Units Rule of Thumb, overall rate by Mill0.5 1.1 1.2 hrs/no Fabricate reinforcement cages- 4.0 - hrs/cage Concreting barrette panels40.0 50.0 55.0 m3/hr Trimming top of barrette panels- 2.4 - days/no Concrete Testing, Coring Test4.0 3.5 2.0 days/no Concrete Testing, Sonic Logging Test- 0.7 - days/no