Barrette Piles

P
PP Admin 👤 Member for 17 years 4 months

Barrette Piles

Task / DescriptionSlow  Ave  Fast   Units Rule of Thumb, overall rate by Mill0.5 1.1 1.2  hrs/no Fabricate reinforcement cages-  4.0 -   hrs/cage Concreting barrette panels40.0 50.0 55.0  m3/hr Trimming top of barrette panels-  2.4 -   days/no Concrete Testing, Coring Test4.0 3.5 2.0  days/no Concrete Testing, Sonic Logging Test-  0.7 -   days/no