Installation
For windows that are not 'built-in' as work proceeds...
- Install & Fix - By Area = 2.0 m2/hr
- Install & Fix - By Girth = 4.0 m/hr
Mastic Pointing = 6.0 m/hr
Doors and Windows
Task / DescriptionSlow Ave Fast Units Mastic Pointing to Frames- 9.5 - m/hr Fix Metal and Timber Windows After Wall Complete- 2.0 - m2/hr Window Glazing- 1.3 - m2/hr Window Glazing, Single Glazed Units- 2.0 - m2/hr Window Glazing, Double Glazed Units- 1.3 - m2/hr
Book navigation for Doors & Window Installation
-
-
-
-
-
-
-
-
-
-
-
Doors & Window Installation
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-