Determine Over Allocated Resource in Primavera P6

G
Galav Dani 👤 Member for 11 years 10 months

Hiii All...

Please someone suggest how to filter out all activities which having over allocation of resources for any proejct in Primavera P6?

please reply everybody.

Z
Zoltan Palffy 👤 Member for 16 years 10 months

Johannes

He already knows the resource that is over loaded the question was how to find the activities that are comtribiting to the overloading.

as your jpg shows you can select view show on bottom resource usage profile and see which activities are in the time frame which is contributing to the overallocation

then you can assign a code to these activities then you can filter them out.

R
Rafael Davila 👤 Member for 22 years 3 months

Deleted by Rafael Davila as to avoid annoying requests to revive this discussion as it is older tha 3 years.

So old no longer Photobucket pictures aer available.

OA01 photo OA01_zps93e95ae1.jpg

Z
Zoltan Palffy 👤 Member for 16 years 10 months

you can identify which activities contribute to the overallocation of the resource.

just look at the timeframe of the activities during the period of overallocation. 

You can select view show on bottom resource usage profile and see whihc activities are in the time frame which is inducated as being overallocated.

then you can assign a code to these activities.  

R
Rafael Davila 👤 Member for 22 years 3 months

Deleted by Rafael Davila as to avoid annoying requests to revive this discussion as it is older tha 3 years.

Forum Sponsor

Top Posters

Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts