Installation Sequences
Industrial and Commercial installations usually commence when false ceilings, floorings and final decorations are substantially complete.
Kitchen Hood Installations are done before false ceiling completion and kitchen equipment is done after the civil wall&floor finishes.
Installation Periods
Size Of Kitchen
Are of Kitchen
Installation Time
100 people
50 m2
3 weeks
500 people
150 m2
5 weeks
1,000 people
275 m2
8 weeks
For individual installations...
Ovens, friers and large mixers etc = 1 man day per item
Sinks, bain maries, washers etc = 2 man days per item
Commercial Kitchen
Task / DescriptionSlow Ave Fast Units Overall Installation for 100 persons or 50m2- 3.0 - wks Overall Installation for 500 persons or 150m2- 5.0 - wks Overall Installation for 1000 persons or 250m2- 8.0 - wks Install Ovens, friers and large mixers etc- 1.0 - mandays Install Sinks, bain maries and washers etc- 2.0 - mandays