Hand Fill & Compact

Loose from side of excavation, including compaction (m3/hr)...

 

Material
Ne 100m
100-200mm
200-300mm
exc 300m

Loose Sand/Soil
0.85
1.02
1.28
1.69

Clay/Heavy Chalk
0.77
0.92
1.16
1.56

Hoging
0.81
0.97
1.20
1.61

Hardcode
0.71
0.84
1.06
1.41