Reinforcement Ratios

P
PP Admin 👤 Member for 17 years 4 months

Reinforcement Ratios

Task / DescriptionSlow  Ave  Fast   Units Pile Cap, Concrete m3 x Ratio = Rebar Tonnes-  14.8 -   % ratio Base Slab, Concrete m3 x Ratio = Rebar Tonnes-  13.2 14.1  % ratio Suspended Slab, Concrete m3 x Ratio = Rebar Tonnes-  20.6 25.6  % ratio Platform Slab, Concrete m3 x Ratio = Rebar Tonnes-  15.6 -   % ratio Columns, Concrete m3 x Ratio = Rebar Tonnes15.8 18.7 28.7  % ratio Walls, Concrete m3 x Ratio = Rebar Tonnes14.7 15.0 -   % ratio