The authors of the Agile Manifesto represented many approaches, methodologies, and frameworks. The common theme was that they had uncovered better ways of developing software. Consequently, the Manifesto was not a recipe with detailed instructions. Rather, it represented a list of suggested ingredients.
The 1, 2, 3 of Primavera P6 Baselines
Primavera P6 Professional allows you to assign up to three user baselines and one project baseline per project. The following article explains these capabilities and how they can be helpful in tracking the overall status of a project and near-term interim variance reports.
Take a look at the following diagram (taken from the Ten Six Primavera P6 training course) that outlines the concept of project and users baselines.
An Introduction to Artificial Intelligence & How it Relates to Project Planning
Introduction
This paper describes and explains the concepts and terminology behind what is today being termed as Artificial Intelligence. Further, it describes how these concepts relate to the field of project management offering opportunity for better, more effective project planning and control.
What Exactly is Artificial Intelligence?
Culture and Successful Projects
Project management has a consistent and unimpressive performance record. The Standish Group’s on-going survey of project performance finds the percentage of projects that were deemed “successful” has hovered in the 25% - 30% range since 1994. Successful projects are defined as those meeting expectations of time, cost, and scope.
In my article, “Successful Projects: What We Really Know,” I highlight factors that improve project outcomes, including:
Merry Christmas from Primavera P6
From Primavera P6 with love :-)

You can download the Project and the Layout from here : https://doduykhuong.com/2017/11/25/merry-christmas-from-primavera-p6/
Project fails because of ineffective Work Breakdown Structure.
Project fails because of ineffective Work Breakdown Structure.
Eliminating Waste in Knowledge Work
Many of us are "knowledge workers." We do not physically create a product. We work in areas that are important to our enterprise, but do not directly serve customers. We work in finance, marketing, technology, or similar functions.
Calculations of Summary Original Durations in Primavera P6
By Yaser A. Al-Bustanji CPCM, ACIArb, PMP, PMI-SP, PMI-RMP, November, 2017
Introduction
This article is a simple guide to understand the data stored in the P6 Original Duration fields that appear in all summary bands such as Project, WBS, Resources and Activity Codes.
How to define Resource Productivity in Primavera P6 and create schedule
When create a schedule, we can based on Resource Productivity to estimate duration.
For example:
- We have a team which can cast 10 m3 of concrete per day (This is Productivity)
- We have an Foundation which take 100 m3 concrete.
- Duration of Foundation activity will be 100 / 10 = 10 days
Now we will do it in Primavera.
Supposed that we have a schedule like below picture: