This is my first note. Actually I have a Persian blog to share my opinion about: Project Management, Project Planning and Control, Strategic Planning and thier softwares. The Latest part of my note is to introduce PowerBI software that is published by Microsoft in 2015. to visit it and my blog follow the link:

http://rezahamzehpour.blogfa.com/   or click here

How does Primavera P6 calculate Planned Value Cost for Activities without linear distribution (using Resource Curves or Manual plan) in Earned Value Management

When we use Earned Value Management technique, we focus on:

  • Planned Value Cost (PV) = Budget At Completion * Schedule % Complete
  • Earned Value Cost (EV) = Budget At Completion * Performance % Complete (usually equal to Activity % Complete)
  • Schedule Variance (SV) = EV - PV
  • SV > 0 : project is good, ahead of schedule

So Planned Value Cost play a very important role here.

By default when we assign resource to activity, the unit is distributed equally (linear). Then calculation of Planned Value is as above.

Oracle Primavera P6 Professional – Get Filter Savvy

How to Mix the ‘And’ and the ‘Or’ Options in One Filter

Building a filter where all the conditions are either ‘And’ or ‘Or’ between each row is pretty straight forward. However, if you want to mix them up a little it’s not so obvious how you should do that in Oracle Primavera P6 Professional. This article will show you how.

Example: I want to find all the milestones in the project that have a date variance that is not equal to zero. In other words, I want to see any milestone that is now sitting on a date other than its baseline date.

Filed Under

Scrum vs. Kanban: What to Choose?

Organizations starting their Agile journey are confronted with an array of choices.  One early decision is, what methodology and process to follow?   

The authors of the Agile Manifesto represented many approaches, methodologies, and frameworks.  The common theme was that they had uncovered better ways of developing software.  Consequently, the Manifesto was not a recipe with detailed instructions.  Rather, it represented a list of suggested ingredients. 

The 1, 2, 3 of Primavera P6 Baselines

Primavera P6 Professional allows you to assign up to three user baselines and one project baseline per project. The following article explains these capabilities and how they can be helpful in tracking the overall status of a project and near-term interim variance reports.

Take a look at the following diagram (taken from the Ten Six Primavera P6 training course) that outlines the concept of project and users baselines.

Filed Under

An Introduction to Artificial Intelligence & How it Relates to Project Planning

Introduction

This paper describes and explains the concepts and terminology behind what is today being termed as Artificial Intelligence. Further, it describes how these concepts relate to the field of project management offering opportunity for better, more effective project planning and control. 

What Exactly is Artificial Intelligence?

Culture and Successful Projects

Project management has a consistent and unimpressive performance record.  The Standish Group’s on-going survey of project performance finds the percentage of projects that were deemed “successful” has hovered in the 25% - 30% range since 1994.  Successful projects are defined as those meeting expectations of time, cost, and scope. 

In my article, “Successful Projects: What We Really Know,” I highlight factors that improve project outcomes, including: