Blogs

Scrum vs. Kanban: What to Choose?

Organizations starting their Agile journey are confronted with an array of choices.  One early decision is, what methodology and process to follow?   

The authors of the Agile Manifesto represented many approaches, methodologies, and frameworks.  The common theme was that they had uncovered better ways of developing software.  Consequently, the Manifesto was not a recipe with detailed instructions.  Rather, it represented a list of suggested ingredients. 

The 1, 2, 3 of Primavera P6 Baselines

Primavera P6 Professional allows you to assign up to three user baselines and one project baseline per project. The following article explains these capabilities and how they can be helpful in tracking the overall status of a project and near-term interim variance reports.

Take a look at the following diagram (taken from the Ten Six Primavera P6 training course) that outlines the concept of project and users baselines.

Filed Under

An Introduction to Artificial Intelligence & How it Relates to Project Planning

Introduction

This paper describes and explains the concepts and terminology behind what is today being termed as Artificial Intelligence. Further, it describes how these concepts relate to the field of project management offering opportunity for better, more effective project planning and control. 

What Exactly is Artificial Intelligence?

Culture and Successful Projects

Project management has a consistent and unimpressive performance record.  The Standish Group’s on-going survey of project performance finds the percentage of projects that were deemed “successful” has hovered in the 25% - 30% range since 1994.  Successful projects are defined as those meeting expectations of time, cost, and scope. 

In my article, “Successful Projects: What We Really Know,” I highlight factors that improve project outcomes, including:

How to define Resource Productivity in Primavera P6 and create schedule

When create a schedule, we can based on Resource Productivity to estimate duration.

For example:

  • We have a team which can cast 10 m3 of concrete per day (This is Productivity)
  • We have an Foundation which take 100 m3 concrete.
  • Duration of Foundation activity will be  100 / 10 = 10 days

Now we will do it in Primavera.

Supposed that we have a schedule like below picture: