Earned Value

How does Primavera P6 calculate Planned Value Cost for Activities without linear distribution (using Resource Curves or Manual plan) in Earned Value Management

When we use Earned Value Management technique, we focus on:

  • Planned Value Cost (PV) = Budget At Completion * Schedule % Complete
  • Earned Value Cost (EV) = Budget At Completion * Performance % Complete (usually equal to Activity % Complete)
  • Schedule Variance (SV) = EV - PV
  • SV > 0 : project is good, ahead of schedule

So Planned Value Cost play a very important role here.

By default when we assign resource to activity, the unit is distributed equally (linear). Then calculation of Planned Value is as above.

Beyond Earned Value Management

If I asked you what the trickiest part of project management was for your enterprise, what would you say?  If you answered managing the diverse projects in your portfolio – you’re not alone. Most businesses work on a variety of projects (whether it be different contract types, duration or dollar amounts) that can be categorized into four major tiers:

Project Controls vs Project Accounting - What's the Difference?

In my career, I've worked across multiple industries and companies and one thing that stands out is the confusion surrounding the function of Project Controls and what it is meant to achieve.  There are Project Accountants, administrators or finance personnel who “do a bit of Project Controls” however, they are actually just producing monthly project financial reports, invoices and cash flows which are only some of the functions that Project Controls is meant to accomplish.

The Case for a Standard Data Reporting Format in a Massive Multi-Contractor Environment

 

If my team and I were on a mission to standardize our program control software, we might perform a benchmarking exercise. I firmly believe if we performed such an exercise, we would find that one-hundred different organizations would have at least one-hundred-five software architectures between them. In fact, that may be optimistic.

BCWS

Budgeted Cost of Work Scheduled (BCWS) is used in Earned Value Analysis

For a fuller understanding, this Wiki entry should be read in conjunction with ACWP and BCWP.

 

BCWS is the cumulative budget cost of doing work as defined in the Base programme.

The total budget value of the activities are added up for each period and plotted cumulatively to give a profile on a graph.

 

Further info can be found at:

http://www.pro