Highlight individual activities in Primavera P6 report

In primavera P6 report, they do not support to highlight individual activity which we want, such as activity behind schedule. Now, I will share with you one way to do this. And in this demo, I want to highlight activity has Total Float (TF) and Variance -BL Project Finish Date (Variance) to red if their value is less than or equal zero to alert for Project Manager and Contractor,

1. First, Right click on report/choose Modify,

2. In Report editor layout, at Detail Area, right click, choose Add Row,

[[wysiwyg_imageupload:5533:height=300,width=500]]

Have your say at Planning Planet's community gathering

The Planning Planet Midlands Kick-Off Meeting will be taking place on Wednesday 18 April 2018 from 18:30 onwards and is available for like-minded Project Controls practitioners in our industry. If you are interested in networking, sharing knowledge and truly learning more about Project Controls then this is most certainly the event for you!

The event will be held at Hayward Suite, Molineux Stadium, Waterloo Road, Wolverhampton, WV1 4QR.

How to use Activity Duration Type in Primavera P6

(If the image is too big, you can read the original article at this link : https://doduykhuong.com/2018/03/25/how-to-use-activity-duration-type-in-primavera-p6/ )

In Primavera P6, when we assign resource to activity there is a equation:

Original Duration x Units/Time = Total Units

(          10 days        x 8 hours/day = 80 hours         )