What Are Some Good Risk Management Techniques?
To properly mitigate risk, a project manager must know how to effectively manage it. The inability to ascertain hazards can cause a project to careen off the rails rather quickly.
To properly mitigate risk, a project manager must know how to effectively manage it. The inability to ascertain hazards can cause a project to careen off the rails rather quickly.
In Primavera P6, there are 2 popular activity type: Task Dependent and Resource Dependent.
So what is the difference?
By choosing Task Dependent or Resource Dependent, P6 will choose what calendar it will use for the activity:
Then it will affect the Original Duration and Finish Date of the activity.
We have Activity A with attribute as below:
For a long time, too long in fact, spreadsheets have been the primary tool that organizations use for budgeting, planning and forecasting. It has become ingrained in the DNA of how organizations function, the foundation of everyday reporting and transmission of vital information.
Often neglected, the subject document is an important piece of paper for construction projects. The document can be used in a variety of ways to improve the project performance and dispute resolutions. I have often seen that the project team believes the document as a burden and useless effort and thus the document is either not maintained properly or in some worse cases the document even doesn’t exists.
Forecasting is an important skill and since the beginning, folks have been using different techniques and procedures to better predict the future. As the technology evolved over time, new techniques and procedures have revolutionized the forecasting capabilities. Forecasting using previous experience is one of the widely used old school methods. This method is good as it is quick and general but precision becoming more and more important in modern projects necessitates the developments of modern forecasting techniques.
Years ago, I begrudgingly took my project management certification (PMP®)exam. I passed. Almost a decade later, I now teach PMP® preparation classes and see the value of the Project Management Book of Knowledge® Guide (PMBOK®)and the rigors of the PMP® certification.
This is my first note. Actually I have a Persian blog to share my opinion about: Project Management, Project Planning and Control, Strategic Planning and thier softwares. The Latest part of my note is to introduce PowerBI software that is published by Microsoft in 2015. to visit it and my blog follow the link:
http://rezahamzehpour.blogfa.com/ or click here
4 Bad (Planning) Habits to Kick this Year
February 15, 2018 | By Dr. Dan Patterson, Guild Fellow of Planning & Scheduling, PMP
When we use Earned Value Management technique, we focus on:
So Planned Value Cost play a very important role here.
By default when we assign resource to activity, the unit is distributed equally (linear). Then calculation of Planned Value is as above.
Building a filter where all the conditions are either ‘And’ or ‘Or’ between each row is pretty straight forward. However, if you want to mix them up a little it’s not so obvious how you should do that in Oracle Primavera P6 Professional. This article will show you how.
Example: I want to find all the milestones in the project that have a date variance that is not equal to zero. In other words, I want to see any milestone that is now sitting on a date other than its baseline date.