0709ELFA

Module
07 Managing Planning & Scheduling
Level
Expert Level (Controls Manager)
Discipline
Forensic Analysis
  • To be able to supervise or manage how others identify the various types of interfaces that can and do exist between work packages and activities, create or make those logical connections,  to ensure that we have horizontal traceability, the objective being to offer constructive criticism to improve the process
  • Can supervise or manage how others identify and apply the various tools/techniques that we can use between work packages and activities to ensure that we have vertical traceability and that our schedules can "roll up" or "roll down" without losing activities or work

0709ELCM

Module
07 Managing Planning & Scheduling
Level
Expert Level (Controls Manager)
Discipline
Cost Management
  • To be able to supervise or manage how others identify the various types of interfaces that can and do exist between work packages and activities, create or make those logical connections,  to ensure that we have horizontal traceability, the objective being to offer constructive criticism to improve the process
  • Can supervise or manage how others identify and apply the various tools/techniques that we can use between work packages and activities to ensure that we have vertical traceability and that our schedules can "roll up" or "roll down" without losing activities or work

0709ELPS

Module
07 Managing Planning & Scheduling
Level
Expert Level (Controls Manager)
Discipline
Planning & Scheduling
  • To be able to supervise or manage how others identify the various types of interfaces that can and do exist between work packages and activities, create or make those logical connections,  to ensure that we have horizontal traceability, the objective being to offer constructive criticism to improve the process
  • Can supervise or manage how others identify and apply the various tools/techniques that we can use between work packages and activities to ensure that we have vertical traceability and that our schedules can "roll up" or "roll down" without losing activities or work

0708ELPC

Module
07 Managing Planning & Scheduling
Level
Expert Level (Controls Manager)
Discipline
Project Controls
  • Be able to supervise or manage the work of others to see how they analyze schedules created by self or others to determine whether or not they are "reliable" when assessed against "best tested and proven" standards as identified in the GPCCAR, the objective being to offer constructive criticism to improve the process
  • Be able to supervise or manage the work of others, to see how they analyze a given problem or situation on the Critical Path , identify which of the various tools/techniques is appropriate to solve or fix the problem then communicate your recommendations to the app

0708ELFA

Module
07 Managing Planning & Scheduling
Level
Expert Level (Controls Manager)
Discipline
Forensic Analysis
  • Be able to supervise or manage the work of others to see how they analyze schedules created by self or others to determine whether or not they are "reliable" when assessed against "best tested and proven" standards as identified in the GPCCAR, the objective being to offer constructive criticism to improve the process
  • Be able to supervise or manage the work of others, to see how they analyze a given problem or situation on the Critical Path , identify which of the various tools/techniques is appropriate to solve or fix the problem then communicate your recommendations to the app

0708ELCM

Module
07 Managing Planning & Scheduling
Level
Expert Level (Controls Manager)
Discipline
Cost Management
  • Be able to supervise or manage the work of others to see how they analyze schedules created by self or others to determine whether or not they are "reliable" when assessed against "best tested and proven" standards as identified in the GPCCAR, the objective being to offer constructive criticism to improve the process
  • Be able to supervise or manage the work of others, to see how they analyze a given problem or situation on the Critical Path , identify which of the various tools/techniques is appropriate to solve or fix the problem then communicate your recommendations to the app

0708ELPS

Module
07 Managing Planning & Scheduling
Level
Expert Level (Controls Manager)
Discipline
Planning & Scheduling
  • Be able to supervise or manage the work of others to see how they analyze schedules created by self or others to determine whether or not they are "reliable" when assessed against "best tested and proven" standards as identified in the GPCCAR, the objective being to offer constructive criticism to improve the process
  • Be able to supervise or manage the work of others, to see how they analyze a given problem or situation on the Critical Path , identify which of the various tools/techniques is appropriate to solve or fix the problem then communicate your recommendations to the app

0707ELPC

Module
07 Managing Planning & Scheduling
Level
Expert Level (Controls Manager)
Discipline
Project Controls
  • Be able to evaluate how others identify what the Critical Path is and be able to analyze it against "best tested and proven" practices, then based on your analysis, communicate the impacts to the relevant or appropriate stakeholders for decisions, the objective being to offer constructive criticism to improve the process
  • Be able to supervise or manage how others identify and analyze any Total and Free Float that exists, then be able to explain to the relevant stakeholders what options they have to use float to the advantage of the project, the objective being to offer construct

0707ELFA

Module
07 Managing Planning & Scheduling
Level
Expert Level (Controls Manager)
Discipline
Forensic Analysis
  • Be able to evaluate how others identify what the Critical Path is and be able to analyze it against "best tested and proven" practices, then based on your analysis, communicate the impacts to the relevant or appropriate stakeholders for decisions, the objective being to offer constructive criticism to improve the process
  • Be able to supervise or manage how others identify and analyze any Total and Free Float that exists, then be able to explain to the relevant stakeholders what options they have to use float to the advantage of the project, the objective being to offer construct

0707ELCM

Module
07 Managing Planning & Scheduling
Level
Expert Level (Controls Manager)
Discipline
Cost Management
  • Be able to evaluate how others identify what the Critical Path is and be able to analyze it against "best tested and proven" practices, then based on your analysis, communicate the impacts to the relevant or appropriate stakeholders for decisions, the objective being to offer constructive criticism to improve the process
  • Be able to supervise or manage how others identify and analyze any Total and Free Float that exists, then be able to explain to the relevant stakeholders what options they have to use float to the advantage of the project, the objective being to offer construct