1003ELPS
Module
10 Managing Change
Level
Expert Level (Controls Manager)
Discipline
Planning & Scheduling
- Is able to manage/supervise the evaluation of the outputs from the 1D, 2D, 3D, 4D, 5D and 6D BIM and modify, adjust or correct those outputs to be appropriate for use as inputs to the planning/scheduling processes
- Is able to manage/supervise the evaluation of the differences between Integrated Project Delivery Process and traditional project processes, and modify, adjust or correct those outputs to be appropriate for use as inputs to the planning/scheduling processes
- Is able to manage/supervise the evaluation of the concepts of "Front End Loading" (FEL) and modify, adju