Updating Progress in P6

Hi all

 

i m facing a problem in P6.

 

I prepared a schedule in P6 loaded with resources i.e Cost and est wt. but when i m updating this schedule it is showing actual value for next month also .

 

for example when i m updating till Apr-11 it is showing actual value for May also .

 

Please help me !

 

for referance please see snap shot

untitled.jpg

Forum Sponsor

Top Posters

Trian Asmoro
1 posts
Soheil Barekat
4 posts
Erkan Polater
9 posts
Luis Jr Ngade
6 posts
Ben Welsher
1 posts
Rohan Dashputre
0 posts
AMECHI ANAKWENZE
2 posts
Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts

Updating Progress in P6

Hi all

 

i m facing a problem in P6.

 

I prepared a schedule in P6 loaded with resources i.e Cost and est wt. but when i m updating this schedule it is showing actual value for next month also .

 

for example when i m updating till Apr-11 it is showing actual value for May also .

 

Please help me !

 

for referance please see snap shot

untitled.jpg

 

Forum Sponsor

Top Posters

Trian Asmoro
1 posts
Soheil Barekat
4 posts
Erkan Polater
9 posts
Luis Jr Ngade
6 posts
Ben Welsher
1 posts
Rohan Dashputre
0 posts
AMECHI ANAKWENZE
2 posts
Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts

Non-critical activities showing up as critical path

Good day,

I built this little schedule, there are only 6 activities, no constraints, everything is pretty much FS, but for some reason the activities are showing up as critical path! When I click on 'schedule' there is an option tab, I have gone in there and changed the Define critical activities and everything is still coming up as critical path!!??!!??!!

Any in-sight would be great!!! Plz & thx :)

Cheers,

Tammy 

Forum Sponsor

Top Posters

Trian Asmoro
1 posts
Soheil Barekat
4 posts
Erkan Polater
9 posts
Luis Jr Ngade
6 posts
Ben Welsher
1 posts
Rohan Dashputre
0 posts
AMECHI ANAKWENZE
2 posts
Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts

Trainee Planner

Greeting prestigious planning community,

 

I finished off school last year and i am currently working for Clough in Australia as a trainee planner, the past 5 months i have been observing and assisting one of the companies major projects happening over in PNG and i believe i have basic understanding of P6 and general Earthworks(thats what we are focused on here)

Next week i am attending a 3 day P6 course(basic i believe) but after that i am not quiet sure what direction to go into, i want to have a broader understanding over the Construction world but i am

Forum Sponsor

Top Posters

Trian Asmoro
1 posts
Soheil Barekat
4 posts
Erkan Polater
9 posts
Luis Jr Ngade
6 posts
Ben Welsher
1 posts
Rohan Dashputre
0 posts
AMECHI ANAKWENZE
2 posts
Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts

Progress Update Problem

I am using P6 and face a problem. When i update the progress, the activities whose %age is between 0%-100% (Like, 50% complete, 70% Complete etc), the bar against such activities in no more remains continuous but it split into 2 parts, 1st part for completed % age and 2nd part for remaining (or critical) % age and there is a gape between these two bars.. I do not know how to overcome this problem. Because the gap between bar seems like there is no work on this activity for some period of time but this is not the actual case.

Forum Sponsor

Top Posters

Trian Asmoro
1 posts
Soheil Barekat
4 posts
Erkan Polater
9 posts
Luis Jr Ngade
6 posts
Ben Welsher
1 posts
Rohan Dashputre
0 posts
AMECHI ANAKWENZE
2 posts
Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts

Progress Update Problem

I am using P6 and face a problem. When i update the progress, the activities whose %age is between 0%-100% (Like, 50% complete, 70% Complete etc), the bar against such activities in no more remains continuous but it split into 2 parts, 1st part for completed % age and 2nd part for remaining (or critical) % age and there is a gape between these two bars.. I do not know how to overcome this problem. Because the gap between bar seems like there is no work on this activity for some period of time but this is not the actual case.

Forum Sponsor

Top Posters

Trian Asmoro
1 posts
Soheil Barekat
4 posts
Erkan Polater
9 posts
Luis Jr Ngade
6 posts
Ben Welsher
1 posts
Rohan Dashputre
0 posts
AMECHI ANAKWENZE
2 posts
Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts

Summary bar and (performance percentages) in P6.

 

Take care of Summary bar in the case of calculating the performance percentages!!

Based on cost sure , to compute the performance percentages  which appear in the column name (performance percentages) in P6 , the summary bar only summaries the activities which have an assign cost.

 

 

 

For each activity:

 primavera use this sequence of steps :

 

1) calculate the earned value:

Forum Sponsor

Top Posters

Trian Asmoro
1 posts
Soheil Barekat
4 posts
Erkan Polater
9 posts
Luis Jr Ngade
6 posts
Ben Welsher
1 posts
Rohan Dashputre
0 posts
AMECHI ANAKWENZE
2 posts
Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts

Forum Sponsor

Top Posters

Trian Asmoro
1 posts
Soheil Barekat
4 posts
Erkan Polater
9 posts
Luis Jr Ngade
6 posts
Ben Welsher
1 posts
Rohan Dashputre
0 posts
AMECHI ANAKWENZE
2 posts
Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts

Can we create relationship in Resouces

K
Kumar Baiju 👤 Member for 15 years 4 months

Hi to all



Can we give the relation for different resources for any activity as we do in activity.

for example if we assign two different resources 1. Engineer and 2nd Draftmen. can we give the relation so that Draftmen will start work after Engineer work finish.Please guide me



Thanks for support in advance

KBJ

Forum Sponsor

Top Posters

Trian Asmoro
1 posts
Soheil Barekat
4 posts
Erkan Polater
9 posts
Luis Jr Ngade
6 posts
Ben Welsher
1 posts
Rohan Dashputre
0 posts
AMECHI ANAKWENZE
2 posts
Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts

Schedule Risk Analysis Execution

Hi guys, as subjected above I just want to know deeply about schedule risk analysis.

 

  1. What is the best software to perform this kind of analysis? Possible by P6?? Pert master is the favourite right?
  2. Is it based on baseline schedule or working schedule??
  3. If you have a thousand activity how come you can perform this analysis by weekly?

Forum Sponsor

Top Posters

Trian Asmoro
1 posts
Soheil Barekat
4 posts
Erkan Polater
9 posts
Luis Jr Ngade
6 posts
Ben Welsher
1 posts
Rohan Dashputre
0 posts
AMECHI ANAKWENZE
2 posts
Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams