Hi all
i m facing a problem in P6.
I prepared a schedule in P6 loaded with resources i.e Cost and est wt. but when i m updating this schedule it is showing actual value for next month also .
for example when i m updating till Apr-11 it is showing actual value for May also .
Please help me !
for referance please see snap shot

Please check the actual progress and data date in hours.
Please check the actual progress and data date in hours.
check this link
http://www.planningplanet.com/forums/primavera-version-pm5-pm6/421689/a…
one possible reason is calendar time affecting data date or actual dates
also check your actual dates