Can we create relationship in Resouces

K
Kumar Baiju 👤 Member for 15 years 4 months

Hi to all



Can we give the relation for different resources for any activity as we do in activity.

for example if we assign two different resources 1. Engineer and 2nd Draftmen. can we give the relation so that Draftmen will start work after Engineer work finish.Please guide me



Thanks for support in advance

KBJ

G
Gary Whitehead 👤 Member for 17 years 3 months

Primavera can't do that, nor can MS Project. Spider may, and I'm not sure about Asta.

But why don't you just have a seperate activity per resource?

 

Also, please don't post the same question in multiple forums. I have deleted the copies.

 

Cheers,

 

G

Forum Sponsor

Top Posters

Trian Asmoro
1 posts
Soheil Barekat
4 posts
Erkan Polater
9 posts
Luis Jr Ngade
6 posts
Ben Welsher
1 posts
Rohan Dashputre
0 posts
AMECHI ANAKWENZE
2 posts
Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts