S Curve re-baseline retrospective comparison
Dear All,
I have re-baselined a percentage complete (earned Man-hour value / budgeted Manhour value) v/s. Time S - Curve at 75% project completion.
Subsequently I have been asked to determine Retrospectively , what was the earned value % when the project was at 50% completion. In such a case should the earned value % be
a) Actual earned value % (say 45% at 50% completion) because the rebaselining had been done AFTER 50% milestone had been completed OR
- Read more about S Curve re-baseline retrospective comparison
- Log in or register to post comments