S Curve re-baseline retrospective comparison

Dear All,

 

I have re-baselined a percentage complete (earned Man-hour value / budgeted Manhour value)  v/s. Time S - Curve at 75% project completion.

Subsequently I have been asked to determine Retrospectively , what was the earned value % when the project was at 50% completion. In such a case should the earned value % be

a) Actual earned value % (say 45% at 50% completion) because the rebaselining had been done AFTER 50% milestone had been completed OR

b) Earned Value % shall be equal to 50% at 50% completion because the S - Curve has been re-baselined.

 

I am aware that Rebaseline affects the forecast / 'To go' part of the S - Curve with the Actual % = Planned % ON the date of the rebaseline. But what about the PAST Actual percentages , do they also become Actual % = Planned % on re-baselining ?

Kindly let me have your opinion.

 

SH

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts