Ladies and Gents,
Just wondering what are the contractual implications of producing a baseline schedule (in P6) that is made up of several projects which are linked together (through external relationships from project to another)!
Thank you,
Rami
Ladies and Gents,
Just wondering what are the contractual implications of producing a baseline schedule (in P6) that is made up of several projects which are linked together (through external relationships from project to another)!
Thank you,
Rami
Hi Rami
As far as I know P6 does a BL project by project. So you'll assign to each project. If you open all of them all BL information is given as well.
I hope I understood your question correctly.
Regards
Dieter