Could you please explain how to add duration to a start or finish milestone.. It's getting changed to the data date everytime I schedule it.. I am using P6 v 8.3
Milestone Duration
Forum Sponsor
Top Posters
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts
Hi Paul
Welcome to Planning Planet.
By definition a milestone has zero duration.
If you add a duration it becomes a task.
Best regards
Mike Testro.