Global Change Summary Task Actual % Complete
Forum TopicDear Experts...Summary task % Complete =((Sum of Completed duration of the Baseline Activities Duration)/(Sum of Baseline Activities Duration))*100.I want to Calcualte the Sumaary task % Complete Based on the Baseline Duration, not based on the Actua...