Sheeted Roofs
Wiki PageSheeted RoofsTask / DescriptionSlow Ave Fast Units PVC Sheeted Roofs, large areas- 50.0 - m2/day PVC Sheeted Roofs, small areas- 40.0 - m2/day Plastic Profiled Sheet Systems- 54.0 - m2/day
Sheeted RoofsTask / DescriptionSlow Ave Fast Units PVC Sheeted Roofs, large areas- 50.0 - m2/day PVC Sheeted Roofs, small areas- 40.0 - m2/day Plastic Profiled Sheet Systems- 54.0 - m2/day
Secant Piling...Task / DescriptionSlow Ave Fast Units Construct 30m dia cofferdam, 255 piles/concrete base- 12.0 - wks
Rule of ThumbTask / DescriptionSlow Ave Fast Units Site Investigation Pre Drilling5.0 4.0 3.0 days/no Ground Excavation, Hydraulic Backhoe- 50.0 - m3/day Bored Piling, 25-70m deep10.0 8.0 6.0 days/no Formwork Fixing- 12.0 - m2/day Reinfor...
Restoration WorksTask / DescriptionSlow Ave Fast Units Façade Cleaning, Water Jetting- 25.0 - m2/day Façade Cleaning, Acid Etching- 9.0 - m2/day Façade Cleaning, Grit Blasting- 12.0 - m2/day Cladding Restoration, Brickwork- 6.5 - m2/d...
RenderingTask / DescriptionSlow Ave Fast Units Large Wall Areas, applied in 2 coats- 2.2 2.7 m2/hr Small Wall Areas, applied in 2 coats- 1.5 1.7 m2/hr Narrow Widths, applied in 2 coats- 1.2 1.4 m2/hr Columns and Beams, applied in 2 coats- ...
Reinforcement RatiosTask / DescriptionSlow Ave Fast Units Pile Cap, Concrete m3 x Ratio = Rebar Tonnes- 14.8 - % ratio Base Slab, Concrete m3 x Ratio = Rebar Tonnes- 13.2 14.1 % ratio Suspended Slab, Concrete m3 x Ratio = Rebar Tonnes- 20.6...
Power SupplyTask / DescriptionSlow Ave Fast Units AC Install 2 no Service transformers, 6 men- 12.0 - days AC Install 2 no Switchgear, 7 men- 12.0 - days AC Install Associated Trays and ladders, 3 men11.0 5.0 - days AC Cable Terminations ...
PlasterboardTask / DescriptionSlow Ave Fast Units Boarding to Plaster dabs3.6 4.0 5.5 m2/hr Boarding to Stud-work/Metal Lathes4.0 5.0 6.7 m2/hr Boarding 12mm nailed to studding- 12.5 - m2/hr Boarding 19mm nailed to studding- 16.5 - m2/hr ...
PartitioningTask / DescriptionSlow Ave Fast Units Timber Studding5.9 6.2 6.8 m/hr Metalwork System (MF) Studding1.6 2.0 2.5 m2/hr Tape, Joint Sand and Top Coat Plasterboard1.1 1.5 2.1 m2/hr Skimming to Plasterboards5.5 6.1 6.7 m2/hr 5mm Hardb...
Manholes and GulleysTask / DescriptionSlow Ave Fast Units Concrete Pre-Cast Manhole Units, 610 x 455 x 51 mm- 1.2 - hrs/no Concrete Pre-Cast Manhole Units, 990 x 610 x 64 mm- 1.6 - hrs/no Brickwork Manhole, 1.0 brick engineering- 0.3 - m...
can anybody please send me a typical programme? (Primavera) maybe for overhead rail works or cut & fill tunnel or tunnel boring or stations Many thanks Stewart Green [email protected]
Hii'm having an issue with P6.7 where i have created a 7 day 24hr calendar for an activity. when i view the duration in hours it is correct but if i convert it to days it calculates it back to the admin timeperiod preference of 8 hr day. so basically...
Kerbs & PavingTask / DescriptionSlow Ave Fast Units Concrete Slabs, laid on bedding, to slight falls2.7 - 4.2 m2/hr Concrete Slabs, laid on bedding, to steep falls2.3 - 2.7 m2/hr Concrete Slabs, laid in mortar, to slight falls1.5 - 2.3 m2/h...
FormworkTask / DescriptionSlow Ave Fast Units Pilecaps, < 0.7m20.9 1.6 2.0 m2/hr Pilecaps, 0.7-2.5m21.6 2.0 2.3 m2/hr Pilecaps, 2.5-3.0m22.0 2.3 2.5 m2/hr Pilecaps, > 3.0m22.3 2.5 3.1 m2/hr Ground Beams, < 0.7m21.1 1.7 1.8 m2/hr Ground Beams...
Floor FinishesTask / DescriptionSlow Ave Fast Units Granolithic Flooring- 3.1 - m2/hr Terrazzo Flooring, in-situ- 3.6 - m2/hr Terrazzo Flooring, pre-cast- 4.6 5.1 m2/hr Mosaic Tiling, 0.045x0.045m- 1.5 2.2 m2/hr Clay, quarry Tiles, smal...
Fencing WorksTask / DescriptionSlow Ave Fast Units Site Hoarding, timber posts, plywood nailed to horizontal rails1.0 1.2 - m/hr Post Erection, Timber / Metal, dig, erect, fix3.3 4.5 - no/hr Post Erection, Concrete, dig, erect, fix3.2 4.0 - ...
Electrical SystemTask / DescriptionSlow Ave Fast Units Railway Station 1st Fix- 38.0 - wks Railway Station 2nd Fix- 16.0 - wks Railway Station T&C- 8.0 - wks Cable Installation, 1 cable laid in trench and protect- 6.2 - m/hr Cable Ins...
Blockwork
I'm trying to build up costs for the installation of 4 x DIA 900mm HDPE pipelines, PN6.4, SDR26, PE100 from the shore into the sea for 1100m in dregded trenches. Installation shall include all material to bury and anchor on shore and to screens under...
Professioanl development for projects controls specailists is a tricky areas with very little on offer. Project managers seem to have a wide range of choice including PRINCE2 and APMP in the UK and PMP Certification for those in the international mar...