Dear Experts...

Summary task % Complete =((Sum of Completed duration of the Baseline Activities Duration)/(Sum of Baseline Activities Duration))*100.

I want to Calcualte the Sumaary task % Complete Based on the Baseline Duration, not based on the Actual Remaining duration. I know to do this in Microsoft Project,...How to do it in primavera using Global Change,,,

I hope my querie is clear...

 

Regards

Mukunda

M
mukunda y 👤 Member for 17 years 6 months

Dear Richard,,,, \

Thank u for reply,,, in UDF we can enter only the text or number or interger, we cannot enter the formula in UDF, ,,, can enter the formula only in Global Change,,dont know much about Global change,,,, hope u understand my problem,,,,

Regards

Mukunda

M
mukunda y 👤 Member for 17 years 6 months

Dear Experts...i am astonishing no reply from day,,, is there no way to do these?

M
mukunda y 👤 Member for 17 years 6 months

I have inserted user_text 1 Column able to write the text in the activities row, not able to write the text, in the WBS row,,,how to do this,,,

 

Regards

Mukunda

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts