P3 Actual/Forecast Cost

A
Ahmed KHR 👤 Member for 15 years 6 months

Dear planners;

I need to make the forecast cost histogramme for the schedule, but I am not sure how?

So, I have to make the update on the % progress cost (Actual Cost/Budgeted Cost Quantities) and P3 generate automaticaly the forecast Costs?

OR I have to update the actual Costs and P3 calculate the forcast progress.

 

Is there any possibilities to keep the progress on 0% (Project start day), and make this job?

 

Your help will be appreciated.

 

V
vimal mohan 👤 Member for 16 years 11 months

Hi Mr.Ahmed

There is two way that you can update the actual cost, 

1. In Auto cost rules, you have "update the percent......" to a)actual cost to date b)Actual qty to date c) Link actual to date and actual this period. In this you have to deselect actual cost to date, so that u p3 will not calculate automatically the cost till the schedule date. You can manually enter the cost incurred and remaining cost will be transferred to balance duration. Then if you generate the report using RC Types, you will get what you want.

2. Suppose you want P3 to calculate the cost with respect to the activity percent, then set the rule in auto cost rules. Using RC Type reports, u will get the forecasted costs.

Remember the update for cost has to be done in Budget window not in resource window.

 

thanks

 

Vimal

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts