Hi everyone,
I am using Primavera PM6 to manage the coming workload of our team.
We have about 95 projects in progress with 4 to 9 activities in each project.
My problem occurs when I open many projects at the same time, the remaining units of some tasks are offset later in timescale and when I try to change the finish date, I get this message :
"Remain Finish Date cannot be earlier than Remain Start Date."
If anybody experienced the same problem, I would appreciate your help.
Thank you
Jean D
Hi
Insert two columns
1. Early Remaining Start & 2. Early Remaining Finish.
For any Inprogress activity, ensure that Early Remaining Start < Early Remaining Finish. If not do it manually by selecting the customize date.
PS: dont forget to move data date after applying the actuals, its cause such kinda problem.
- Ravi
I also get this error when I have only one project open. In addition, I get another error that referes to the Remaining Start and Remaining Finish: Remaining Start cannot be Null; Remaining Finish cannot be Null.