Remain Finish Date vs Remain Start Date.

Hi everyone,

I am using Primavera PM6 to manage the coming workload of our team.

We have about 95 projects in progress with 4 to 9 activities in each project.

My problem occurs when I open many projects at the same time, the remaining units of some tasks are offset later in timescale and when I try to change the finish date, I get this message :

"Remain Finish Date cannot be earlier than Remain Start Date."

If anybody experienced the same problem, I would appreciate your help.

Thank you

Jean D

R
Ravi Katare 👤 Member for 11 years 10 months

Hi

Insert two columns

1. Early Remaining Start & 2. Early Remaining Finish.

For any Inprogress activity, ensure that Early Remaining Start < Early Remaining Finish. If not do it manually by selecting the customize date.

PS: dont forget to move data date after applying the actuals, its cause such kinda problem.

 

- Ravi

M
M Carey 👤 Member for 12 years 3 months

I also get this error when I have only one project open. In addition, I get another error that referes to the Remaining Start and Remaining Finish: Remaining Start cannot be Null; Remaining Finish cannot be Null.

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts