Trouble Exporting MSProject 2007 files to Primavera Contractor

I am having huge problems trying to export a project created in MS Project (by my owner) into Primavera's P4 Contractor.

I need help so that I don't have to recreate the entire project from scratch. Anyone know a way or a file conversion utility to accomplish this?

W
William (Bill) Drew 👤 Member for 15 years 2 months

Primavera is not compatible with MSP 2007. You must save your MSP either as MSP 2003 or as an XML file and then import it into P4. 