Contractor Mandays Claim

Forum Topic

I have this issue: The project is currently incurring delays due to delay in issuance of the client of the required drawings. That's given. We have not assessed yet (final assessment) the impact. However, we received the letter from the contractor cl...

Oct 6, 2011

having item float with another item

Forum Topic

i currently have an item on a schedule called "shutdown"i have introduced another item called "give 7 day notice prior to shutdown" and made its succesor "shutdown" and its pred "notice to proceed" i want the date for this new item to always be 7 day...

Oct 6, 2011

P6.2 Strange Total Float values for Group/Sort Summary Bars

Forum Topic

This is a great resource you are putting together here. I'm hoping someone can give me a bit of insight into an issue with P6.2 I'm currently having.I'm attempting to analyse a series of very large schedules and have used the multiple float path sche...

Oct 7, 2011

EPCM Scheduling

Forum Topic

Hi PPI have been working as a construction planner for the past two years' but for the last six month I join a new company as a Junior EPCM Planner. Basicly my role is to plan from FEL1 right through to Exacuation.my idea would be to build a basic FE...

Oct 7, 2011

Weekend Quiz # 2

Forum Topic

Hi Puzzlers Three simple trivia questions - in the topic of Science - Music and Sport. 1.  What was Isaac Newton's most famous invention - still used today? Ans The Cat Flap 2.  What was Mozart's most popular melody? Ans Twinkle Twinkle Little Star 3...

Oct 7, 2011

Primavera

Forum Topic

Hello, I have been using asta powerproject for 4 years preparing programmes, reporting progress, resourcing programmes etc. I have noticed that a lot of planners in Australia use Prima Vera instead, as I am interested in working there sometime in the...

Oct 7, 2011

P6.2.1, Baseline Query

Forum Topic

Appreciate your help on this one....I am getting the following error when trying to update the Baseline with Current Actviity changes for the period...   2011-08-04T16:20:50 SEVERE Errors located: RemainingDuration: Remaining Duration cannot be great...

Aug 5, 2011

P6.2.1, Baseline Query

Forum Topic

Appreciate your help on this one....I am getting the following error when trying to update the Baseline with Current Actviity changes for the period...   2011-08-04T16:20:50 SEVERE Errors located: RemainingDuration: Remaining Duration cannot be great...

Aug 5, 2011

MSP 2007 Formulae

Forum Topic

Hi, Request your help in this querry of mine.Following is my querry and requestto revert back I have uplaoded my schedule. It is resource loaded and non resource loadedand has various formulae in the columns, I have tried. Please correct mymistakes i...

Aug 5, 2011

Survival Island

Forum Topic

There was this island surrounded by a sea infested of hungry man eating sharks. The island is 100% covered with very dry vegetation and suddenly a fire start along all north shore. Assume it never rains. The wind blows from north to south. The man is...

Aug 5, 2011

Performance % Complete Behaviour

Forum Topic

Hi folks, I'm just a little confuse on how exactly Performance % Complete behaves when it rolls up. I have all my activities resource and cost loaded but it doesn't rollup. Below are my current settings: Calculations Tab: $1 WBS Earned Value: Activit...

Aug 5, 2011

Performance % Complete Behaviour

Forum Topic

Hi folks, I'm just a little confuse on how exactly Performance % Complete behaves when it rolls up. I have all my activities resource and cost loaded but it doesn't rollup. Below are my current settings: Calculations Tab: $1 WBS Earned Value: Activit...

Aug 5, 2011

Baseline Updating

Forum Topic

Getting this error...Any suggestions? tks.     2011-08-05T15:23:49 SEVERE Field not set:ActivityObjectId when creating ActivityNote.

Aug 5, 2011

planned % of completion

Forum Topic

Hai, AllCan you explain,how to measure the planned % of completion(for the purpose to generate the project prrogress planned curve)in diffrent future analysis dates(monthly/weekly) from the baseline programme by using P6Regards,

Aug 6, 2011

Scheduling for Complex Projects

Forum Topic

Based on the CIOB Guide to Good Practice in the Management of time in Complex Projects, this new 2 day workshop will be run in Doha, 9thand 10th October. -  Download the brochure: http://www.mosaicprojects.com.au/PDF/Schedule-Doha.pdf - See more on s...

Aug 6, 2011

P6 V7 Remining Units

Forum Topic

Just upgraded to P6V7 Something seems wring in the remaining Units field does any body have anyideas ?   Budgeted Labour Units 538Hrs Physical % Complete is 38 % Unit % Complete is 38 % Actual Units = 269 (Automatic update) At Completion Labour Units...

Aug 8, 2011

Curva S

Forum Topic

I wonder how best to generate an S-Curve physical progress without resource allocation. Using MS Project 2003 / 2007. Thank you.

Aug 8, 2011

Showing "% Complete" on Y-Axis of resource profile in P6.7

Forum Topic

Hi All,   I have searched for this answer but cannot find,   At the moment my resource profile (S-curve) in P6 shows time on X-axis and units on Y-axis. (Standard format)   What box do I tick to instead show "% complete" on the Y-axis (based on budge...

Aug 9, 2011