Appreciate your help on this one....I am getting the following error when trying to update the Baseline with Current Actviity changes for the period...
2011-08-04T16:20:50
SEVERE
Errors located: RemainingDuration: Remaining Duration cannot be greater than At Completion Duration.
I have reviewed all activities, no where is the RD greater than the At Completion Duration???
Any suggestions about what settings is required for updating Baselines??
Much appreciated...
Craig
Craig
1st The difference may be a second
2nd (more likely) check your resource assignments; in general this error is from there.
Did you schedule (F9) before? This sometimes eliminates this error.
To find the activity responsible for this error, try "check project integrity". It will show that activity.
If this won't work for the project, disconnect the baseline and do the same with it.
By the way: Is your baseline "as built"?
Good luck!
Dieter