P6 V7 Remining Units

J
Jay Stadler 👤 Member for 14 years 10 months

Just upgraded to P6V7

Something seems wring in the remaining Units field does any body have anyideas ?

 

Budgeted Labour Units 538Hrs

Physical % Complete is 38 %

Unit % Complete is 38 %

Actual Units = 269 (Automatic update)

At Completion Labour Units is 707.9 Hrs (Automatic update)

Remaining Labour Units is 438.9

 

Setting

 

Admin Preferences

ETC=Remaining cost for Activity

 

Activity Settings

 

Task Dependent

Fixed Duration and Units

Physical

 

Project Settings

Link Budget and At Completion for not Started activities

Reset Remaining Duration and Units to Original

Subtract Actual from at Completions

 

When I change At Completion labour Units to 538 it recalculate Units % Complete to 50 % and Change Remaining Labour Units to 269

 

The answer I want is the following

Budget = 538 Hrs

% Complete is 38 %

Earned value is 204

Remaining Hours is 333

 

How do I get P6V7 to do this ?

K
kevin kianpour 👤 Member for 15 years 8 months

I believe, when Physical PCT is used, both % and remaining durations must me updated. Based on remining duration and units per day, Remining Hours are calculated. Also the earned value calculation method should ve visited, under, wbs screen, earned value tab. Make sure the Performance measure type is set to activity pct.

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts