P6.2.1, Baseline Query

Appreciate your help on this one....I am getting the following error when trying to update the Baseline with Current Actviity changes for the period...

 

2011-08-04T16:20:50
SEVERE
Errors located: RemainingDuration: Remaining Duration cannot be greater than At Completion Duration.

I have reviewed all activities, no where is the RD greater than the At Completion Duration???

 

Any suggestions about what settings is required for updating Baselines??

 

Much appreciated...

 

Craig

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts