Performance % Complete Behaviour

Hi folks,

I'm just a little confuse on how exactly Performance % Complete behaves when it rolls up.

I have all my activities resource and cost loaded but it doesn't rollup. Below are my current settings:

Calculations Tab: $1

WBS Earned Value: Activity Percent Complete

Advance Scheduling: enabled recalculate assignment

Group & Sort: show total

Any help would be very much appreciated.

thanks.

Don

Forum Sponsor

Top Posters

Trian Asmoro
1 posts
Soheil Barekat
4 posts
Erkan Polater
9 posts
Luis Jr Ngade
6 posts
Ben Welsher
1 posts
Rohan Dashputre
0 posts
AMECHI ANAKWENZE
2 posts
Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts