Hi folks,
I'm just a little confuse on how exactly Performance % Complete behaves when it rolls up.
I have all my activities resource and cost loaded but it doesn't rollup. Below are my current settings:
Calculations Tab: $1
WBS Earned Value: Activity Percent Complete
Advance Scheduling: enabled recalculate assignment
Group & Sort: show total
Any help would be very much appreciated.
thanks.
Don