Performance % Complete Behaviour

Hi folks,

I'm just a little confuse on how exactly Performance % Complete behaves when it rolls up.

I have all my activities resource and cost loaded but it doesn't rollup. Below are my current settings:

Calculations Tab: $1

WBS Earned Value: Activity Percent Complete

Advance Scheduling: enabled recalculate assignment

Group & Sort: show total

Any help would be very much appreciated.

thanks.

Don

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts