Hi All,
I have searched for this answer but cannot find,
At the moment my resource profile (S-curve) in P6 shows time on X-axis and units on Y-axis. (Standard format)
What box do I tick to instead show "% complete" on the Y-axis (based on budgeted units, not actual values)
I have tried changing "Time Units" to "Show as Percentage" in the User Preferences, no change.
Many thanks
Sam D
Hi,
You can partially achieve this by dividing the resource allocation interval totals by the whole contract amount or discipline total. It depends the scope of S-Curve. (Resource Assignments-->(Right Pane) Display-->Spreadsheet Options) By doing this you will have a value between 0 and 1 on the Y axis and I think this can somehow facilitate the interpretation of S-Curve.
Changing "Time Units" to "Show as Percentage" in the User Preferences enables you to view all the data columns titled as '.... Units/Time' in percentage wise such as the ones in Resource Dictionary or under Resources tab of Activity Details Table.
Regards,
baris