Performance % Complete Behaviour

Hi folks,

I'm just a little confuse on how exactly Performance % Complete behaves when it rolls up.

I have all my activities resource and cost loaded but it doesn't rollup. Below are my current settings:

Calculations Tab: $1

WBS Earned Value: Activity Percent Complete

Advance Scheduling: enabled recalculate assignment

Group & Sort: show total

Any help would be very much appreciated.

thanks.

Don

J
Jash Sales 👤 Member for 16 years 6 months

Hi Don,

Have you assigned already a budgeted cost to your activities? and what type of activity % complete you assigned? if you didnt assign any cost to any of your activities then theres nothing to be rolled up. also, if theres no percent progress in your assigned activity % complete still not rolled up. investigate this two things by showing in your windows column the budgeted cost, performance %complete, and activity % complete type that you used.

jash

Forum Sponsor

Top Posters

Trian Asmoro
1 posts
Soheil Barekat
4 posts
Erkan Polater
9 posts
Luis Jr Ngade
6 posts
Ben Welsher
1 posts
Rohan Dashputre
0 posts
AMECHI ANAKWENZE
2 posts
Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts