0704CLCM

Module
07 Managing Planning & Scheduling
Level
Specialist (Controls Practitioner / Senior Project Manager)
Discipline
Cost Management
  • Is able to apply the most appropriate or correct logical relationships, in a way that most realistically reflects what the real or true execution sequence is, and be able to explain that to other stakeholders
  • Is able to analyze schedules created by one’s self or others, analyze to see if there is any redundant logic, and if so, correct or suggest other make corrections to eliminate it
  • Is able to analyze schedules created by self or others, identify any "open ends" or "hangars" and correct or suggest others to make corrections to eliminate or fix it
  • Is able to ap

0704CLPS

Module
07 Managing Planning & Scheduling
Level
Specialist (Controls Practitioner / Senior Project Manager)
Discipline
Planning & Scheduling
  • Is able to apply the most appropriate or correct logical relationships, in a way that most realistically reflects what the real or true execution sequence is, and be able to explain that to other stakeholders
  • Is able to analyze schedules created by one’s self or others, analyze to see if there is any redundant logic, and if so, correct or suggest other make corrections to eliminate it
  • Is able to analyze schedules created by self or others, identify any "open ends" or "hangars" and correct or suggest others to make corrections to eliminate or fix it
  • Is able to ap

0703CLPC

Module
07 Managing Planning & Scheduling
Level
Specialist (Controls Practitioner / Senior Project Manager)
Discipline
Project Controls
  • Is able to identify what topics should be covered in a schedule development meeting, who should attend and what the role/responsibilities of each participant should be and to facilitate or lead such a meeting
  • Is able to select, choose or recommend the appropriate level of detail for any given phase in the asset/project life span, along with being able to analyze and assess the constraints and assumptions appropriate for that phase
  • Is able to select the "best" or "most appropriate" coding structure from amongst the various Standardized WBS structures, and be able to crea

0703CLFA

Module
07 Managing Planning & Scheduling
Level
Specialist (Controls Practitioner / Senior Project Manager)
Discipline
Forensic Analysis
  • Is able to identify what topics should be covered in a schedule development meeting, who should attend and what the role/responsibilities of each participant should be and to facilitate or lead such a meeting
  • Is able to select, choose or recommend the appropriate level of detail for any given phase in the asset/project life span, along with being able to analyze and assess the constraints and assumptions appropriate for that phase
  • Is able to select the "best" or "most appropriate" coding structure from amongst the various Standardized WBS structures, and be able to crea

0703CLCM

Module
07 Managing Planning & Scheduling
Level
Specialist (Controls Practitioner / Senior Project Manager)
Discipline
Cost Management
  • Is able to identify what topics should be covered in a schedule development meeting, who should attend and what the role/responsibilities of each participant should be and to facilitate or lead such a meeting
  • Is able to select, choose or recommend the appropriate level of detail for any given phase in the asset/project life span, along with being able to analyze and assess the constraints and assumptions appropriate for that phase
  • Is able to select the "best" or "most appropriate" coding structure from amongst the various Standardized WBS structures, and be able to crea

0703CLPS

Module
07 Managing Planning & Scheduling
Level
Specialist (Controls Practitioner / Senior Project Manager)
Discipline
Planning & Scheduling
  • Is able to identify what topics should be covered in a schedule development meeting, who should attend and what the role/responsibilities of each participant should be and to facilitate or lead such a meeting
  • Is able to select, choose or recommend the appropriate level of detail for any given phase in the asset/project life span, along with being able to analyze and assess the constraints and assumptions appropriate for that phase
  • Is able to select the "best" or "most appropriate" coding structure from amongst the various Standardized WBS structures, and be able to crea

0702CLPC

Module
07 Managing Planning & Scheduling
Level
Specialist (Controls Practitioner / Senior Project Manager)
Discipline
Project Controls
  • Assuming you were asked to create an SOP, be able to explain how you would design an SOP for Project Controls
  • Be able to list and explain the components or elements which should be included in any SOP
  • Be able to demonstrate how to use Double Loop Learning to modify or update your SOP

0702CLFA

Module
07 Managing Planning & Scheduling
Level
Specialist (Controls Practitioner / Senior Project Manager)
Discipline
Forensic Analysis
  • Assuming you were asked to create an SOP, be able to explain how you would design an SOP for Forensic Analysis
  • Be able to list and explain the components or elements which should be included in any SOP
  • Be able to demonstrate how to use Double Loop Learning to modify or update your SOP

0702CLCM

Module
07 Managing Planning & Scheduling
Level
Specialist (Controls Practitioner / Senior Project Manager)
Discipline
Cost Management
  • Assuming you were asked to create an SOP, be able to explain how you would design an SOP for Cost Budgeting/Cost Control
  • Be able to list and explain the components or elements which should be included in any SOP
  • Be able to demonstrate how to use Double Loop Learning to modify or update your SOP

0702CLPS

Module
07 Managing Planning & Scheduling
Level
Specialist (Controls Practitioner / Senior Project Manager)
Discipline
Planning & Scheduling
  • Assuming you were asked to create an SOP, be able to explain how you would design an SOP for planning/scheduling
  • Be able to list and explain the components or elements which should be included in any SOP
  • Be able to demonstrate how to use Double Loop Learning to modify or update your SOP