0706CLPS

Module
07 Managing Planning & Scheduling
Level
Specialist (Controls Practitioner / Senior Project Manager)
Discipline
Planning & Scheduling
  • Is able to identify the types of resources, assign them to the appropriate activity and be able to explain/justify/rationalize these assignments to stakeholders
  • Be able to create a presentation illustrating the tradeoffs between time and cost, how you calculated those tradeoffs and how you communicated the monetary impacts then facilitated the decision makers to evaluate their options to come up with a decision
  • Be able to calculate the impact of learning curves to the schedule, make the changes to the durations, then be able to explain/justify/rationalize the impact to

0706CLCM

Module
07 Managing Planning & Scheduling
Level
Specialist (Controls Practitioner / Senior Project Manager)
Discipline
Cost Management
  • Is able to identify the types of resources, assign them to the appropriate activity and be able to explain/justify/rationalize these assignments to stakeholders
  • Be able to create a presentation illustrating the tradeoffs between time and cost, how you calculated those tradeoffs and how you communicated the monetary impacts then facilitated the decision makers to evaluate their options to come up with a decision
  • Be able to calculate the impact of learning curves to the schedule, make the changes to the durations, then be able to explain/justify/rationalize the impact to

0706CLFA

Module
07 Managing Planning & Scheduling
Level
Specialist (Controls Practitioner / Senior Project Manager)
Discipline
Forensic Analysis
  • Is able to identify the types of resources, assign them to the appropriate activity and be able to explain/justify/rationalize these assignments to stakeholders
  • Be able to create a presentation illustrating the tradeoffs between time and cost, how you calculated those tradeoffs and how you communicated the monetary impacts then facilitated the decision makers to evaluate their options to come up with a decision
  • Be able to calculate the impact of learning curves to the schedule, make the changes to the durations, then be able to explain/justify/rationalize the impact to

0706CLPC

Module
07 Managing Planning & Scheduling
Level
Specialist (Controls Practitioner / Senior Project Manager)
Discipline
Project Controls
  • Is able to identify the types of resources, assign them to the appropriate activity and be able to explain/justify/rationalize these assignments to stakeholders
  • Be able to create a presentation illustrating the tradeoffs between time and cost, how you calculated those tradeoffs and how you communicated the monetary impacts then facilitated the decision makers to evaluate their options to come up with a decision
  • Be able to calculate the impact of learning curves to the schedule, make the changes to the durations, then be able to explain/justify/rationalize the impact to

0705CLPS

Module
07 Managing Planning & Scheduling
Level
Specialist (Controls Practitioner / Senior Project Manager)
Discipline
Planning & Scheduling
  • Is able to create and/or update Resource Dictionaries, then explain or demonstrate how they can or should be assigned to an activity
  • Is able to identify the types of resources, assign them to the appropriate activity and be able to explain/justify/rationalize these assignments to stakeholders

0705CLCM

Module
07 Managing Planning & Scheduling
Level
Specialist (Controls Practitioner / Senior Project Manager)
Discipline
Cost Management
  • Is able to create and/or update Resource Dictionaries, then explain or demonstrate how they can or should be assigned to an activity
  • Is able to identify the types of resources, assign them to the appropriate activity and be able to explain/justify/rationalize these assignments to stakeholders

0705CLFA

Module
07 Managing Planning & Scheduling
Level
Specialist (Controls Practitioner / Senior Project Manager)
Discipline
Forensic Analysis
  • Is able to create and/or update Resource Dictionaries, then explain or demonstrate how they can or should be assigned to an activity
  • Is able to identify the types of resources, assign them to the appropriate activity and be able to explain/justify/rationalize these assignments to stakeholders

0705CLPC

Module
07 Managing Planning & Scheduling
Level
Specialist (Controls Practitioner / Senior Project Manager)
Discipline
Project Controls
  • Is able to create and/or update Resource Dictionaries, then explain or demonstrate how they can or should be assigned to an activity
  • Is able to identify the types of resources, assign them to the appropriate activity and be able to explain/justify/rationalize these assignments to stakeholders

0704CLPC

Module
07 Managing Planning & Scheduling
Level
Specialist (Controls Practitioner / Senior Project Manager)
Discipline
Project Controls
  • Is able to apply the most appropriate or correct logical relationships, in a way that most realistically reflects what the real or true execution sequence is, and be able to explain that to other stakeholders
  • Is able to analyze schedules created by one’s self or others, analyze to see if there is any redundant logic, and if so, correct or suggest other make corrections to eliminate it
  • Is able to analyze schedules created by self or others, identify any "open ends" or "hangars" and correct or suggest others to make corrections to eliminate or fix it
  • Is able to ap

0704CLFA

Module
07 Managing Planning & Scheduling
Level
Specialist (Controls Practitioner / Senior Project Manager)
Discipline
Forensic Analysis
  • Is able to apply the most appropriate or correct logical relationships, in a way that most realistically reflects what the real or true execution sequence is, and be able to explain that to other stakeholders
  • Is able to analyze schedules created by one’s self or others, analyze to see if there is any redundant logic, and if so, correct or suggest other make corrections to eliminate it
  • Is able to analyze schedules created by self or others, identify any "open ends" or "hangars" and correct or suggest others to make corrections to eliminate or fix it
  • Is able to ap