Alter Performance % Complete
Hi all,
I am a planner based in the Middle East still learning different aspects of Primavera P6.I have a doubt actually which I came across on a previous post in this forum but had no proper answers.
My question is,is it posssible to alter the performance % of a particular activity when we have assigned cost to it?
As far as I understand,
The performance % is calculated as Earned Value Cost = Activity % Complete X Budgeted Cost ( in the baseline )
- Read more about Alter Performance % Complete