Alter Performance % Complete

Hi all,

 

I am a planner based in the Middle East still learning different aspects of Primavera P6.I have a doubt actually which I came across on a previous post in this forum but had no proper answers.

My question is,is it posssible to alter the performance % of a particular activity when we have assigned cost to it?

As far as I understand,

The performance % is calculated as Earned Value Cost = Activity % Complete X Budgeted Cost ( in the baseline )

Forum Sponsor

Top Posters

James Williams
74 posts
Saqib Ullah
1 posts
Luyanda Ndlumbini
2 posts
Jeff Waldrop
6 posts
Robert Roy
1 posts
Tony Wright
4 posts
Arshman
0 posts
Stan Remiszewski
1 posts
GeoVe
0 posts
JAGAN REDDY MUSUKU
0 posts

Freshers/beginner/planning to start a career in planning

hello planners here,

I am glad to see such a wonderful site prepared for the planners around the globe.

I am Thomas from India, I have overall 5 years in poject and shutdowns/turnaround in oil and gas field (execution field)

I am here to find support and help from you all so that peoples like me can get info on how to start a career in planning/scheduling.

Forum Sponsor

Top Posters

James Williams
74 posts
Saqib Ullah
1 posts
Luyanda Ndlumbini
2 posts
Jeff Waldrop
6 posts
Robert Roy
1 posts
Tony Wright
4 posts
Arshman
0 posts
Stan Remiszewski
1 posts
GeoVe
0 posts
JAGAN REDDY MUSUKU
0 posts

unit % complete not able to update in Status bar

Hi guys,

I am facing a problem that only for specfic activities i am not able to update any Unit % complete or remaining duration in the status bar.

And also it is showing the critical path in the primavera P6.

The schedule has negative float while submitting to client and it is approved.

Can any one guide how can i resolve the problem ????

Urgent PLzzzzzz

Forum Sponsor

Top Posters

James Williams
74 posts
Saqib Ullah
1 posts
Luyanda Ndlumbini
2 posts
Jeff Waldrop
6 posts
Robert Roy
1 posts
Tony Wright
4 posts
Arshman
0 posts
Stan Remiszewski
1 posts
GeoVe
0 posts
JAGAN REDDY MUSUKU
0 posts

Forum Sponsor

Top Posters

James Williams
74 posts
Saqib Ullah
1 posts
Luyanda Ndlumbini
2 posts
Jeff Waldrop
6 posts
Robert Roy
1 posts
Tony Wright
4 posts
Arshman
0 posts
Stan Remiszewski
1 posts
GeoVe
0 posts
JAGAN REDDY MUSUKU
0 posts

Resetting the Baseline on a Progress with Progress Applied?

K
KT G23 👤 Member for 10 years 11 months

Hi

 

I was just wondering if anyone cold provide any guidnace on resetting the baseline in P6 when your project already has progress in it?

For example, I have a project that has progress applied for 6 months and now have a Compensation Event (Delay Claim) which needs to be added to baseline.

Forum Sponsor

Top Posters

James Williams
74 posts
Saqib Ullah
1 posts
Luyanda Ndlumbini
2 posts
Jeff Waldrop
6 posts
Robert Roy
1 posts
Tony Wright
4 posts
Arshman
0 posts
Stan Remiszewski
1 posts
GeoVe
0 posts
JAGAN REDDY MUSUKU
0 posts

Delay by total float vs. delay by variance

D
Dura Cell 👤 Member for 15 years 6 months

Hi All!



We are using P6 in our project, one of our consultant is calculating activity delays using the variance dates (BL FInish - Finish), my point of view as a planner is the actual delays in the activity can be viewed once we run the schedule as P6 determines delay after calculating the schedule (critical path).



I would like to ask what is the effective way of computing delays in the activity?

Is it by total float or is it by variance? Any advantages or disadvantages of these two?



Many Thanks!

Forum Sponsor

Top Posters

James Williams
74 posts
Saqib Ullah
1 posts
Luyanda Ndlumbini
2 posts
Jeff Waldrop
6 posts
Robert Roy
1 posts
Tony Wright
4 posts
Arshman
0 posts
Stan Remiszewski
1 posts
GeoVe
0 posts
JAGAN REDDY MUSUKU
0 posts

Resource Assignment summary

S
Sunil Babu 👤 Member for 15 years 7 months

Dear All,

After assigning a resource when I open Project - Resource assignment it is showing blank . Is there any settings that has to be changed inorder to show the resource summary ( Budgeted units) by month. Any thing related to report settings to be modified ?

I already added primary resource column and it is displaying that resource.

Awaitig your valuable reply.

Best Regards,

Sunil.

Forum Sponsor

Top Posters

James Williams
74 posts
Saqib Ullah
1 posts
Luyanda Ndlumbini
2 posts
Jeff Waldrop
6 posts
Robert Roy
1 posts
Tony Wright
4 posts
Arshman
0 posts
Stan Remiszewski
1 posts
GeoVe
0 posts
JAGAN REDDY MUSUKU
0 posts

Forum Sponsor

Top Posters

James Williams
74 posts
Saqib Ullah
1 posts
Luyanda Ndlumbini
2 posts
Jeff Waldrop
6 posts
Robert Roy
1 posts
Tony Wright
4 posts
Arshman
0 posts
Stan Remiszewski
1 posts
GeoVe
0 posts
JAGAN REDDY MUSUKU
0 posts

Forum Sponsor

Top Posters

James Williams
74 posts
Saqib Ullah
1 posts
Luyanda Ndlumbini
2 posts
Jeff Waldrop
6 posts
Robert Roy
1 posts
Tony Wright
4 posts
Arshman
0 posts
Stan Remiszewski
1 posts
GeoVe
0 posts
JAGAN REDDY MUSUKU
0 posts

Time Impact Analysis Schedule

A
Ahmet Tuter 👤 Member for 13 years 4 months

Hello,

I was asked to prepare an example TIA - Time Impact Analysis Schedule in P6.

To do this, I would first prepare a normal baseline schedule, and then, assign delays to certain activities and prepare a second, delayed schedule? And calculate a variance?

How can i do this? Time ipact schedule is just the delayed version of the normal schedule?

In primavera what commands or tools there are for this?

Forum Sponsor

Top Posters

James Williams
74 posts
Saqib Ullah
1 posts
Luyanda Ndlumbini
2 posts
Jeff Waldrop
6 posts
Robert Roy
1 posts
Tony Wright
4 posts
Arshman
0 posts
Stan Remiszewski
1 posts
GeoVe
0 posts
JAGAN REDDY MUSUKU
0 posts