unit % complete not able to update in Status bar

Hi guys,

I am facing a problem that only for specfic activities i am not able to update any Unit % complete or remaining duration in the status bar.

And also it is showing the critical path in the primavera P6.

The schedule has negative float while submitting to client and it is approved.

Can any one guide how can i resolve the problem ????

Urgent PLzzzzzz

Z
Zoltan Palffy 👤 Member for 16 years 10 months

need more info

1. Did you look at the TYPE of activity ?

Level of efforts or summary wbs typs of activities are based on the underlaying activities.

2. I would hope that it is showing the critical path in p6 that is what the program is all about hence the name critical ptha method CPM 

3. Why does the schedule have negative float either becasue you are behind schedule or you have not progressed your schedule correctly. 

4. I do not undrstand the title of the post 

unit % complete not able to update in Status bar

you mentioned nothing about units 

have you checked your calculations settings ?

when updating actual units or cost 

subtract actual for at completion

also recalculate actual units and cost when duration % complete changes

and Link actual and actaul this period units and cost 

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts