Hello,
I was asked to prepare an example TIA - Time Impact Analysis Schedule in P6.
To do this, I would first prepare a normal baseline schedule, and then, assign delays to certain activities and prepare a second, delayed schedule? And calculate a variance?
How can i do this? Time ipact schedule is just the delayed version of the normal schedule?
In primavera what commands or tools there are for this?
Hi,
I write an article regarding How to perform Time Impact Analysis / Window Analysis in Primavera P6.
If you're interested, kindly read it here https://doduykhuong.com/2016/09/10/how-to-perform-time-impact-analysis-window-analysis-in-primavera-p6/
Hi Andrew,
I am in the process of making a cliam, I accept I don't have good experience with the Claims. So I request you to help me out with some steps.
Have an accepted baseline schedule against which to make a comparission ( I am having one)
This will illustrate the potential delay to the project caused by the delay event, repeat the exercise for any subsequent delays. ( I wish to know,if can we add different events into this prepared on and how because if on different date with different updated dates ? if we have monthly updated programs and each one has different events(dated prior to data date) how will we collaborate it into one and how are we able to compare? should we do it seperately and analyse with may be a spread sheet?)
I know these are silly question but requesting your help. I read some books and slides on steps, but something is missing with where should I add the fragnet(Q3). I have a multicritical path project too so its a bit complex and it's on going project . The confusing part is if we are taking the program to add an event immediately after the data date then whats the use of latest updated one & where is it used? .
To prepare a TIA I believe you should,
This will illustrate the potential delay to the project caused by the delay event, repeat the exercise for any subsequent delays.
there are no commands for this