Bell Ground Anchors
Wiki PageBell Ground AnchorsTask / DescriptionSlow Ave Fast Units Uncased Anchors, 10m long- 2.0 - no/day Top Cased Anchors, 15m long- 1.0 - no/day Anchors stressing- 2.2 - no/day
Bell Ground AnchorsTask / DescriptionSlow Ave Fast Units Uncased Anchors, 10m long- 2.0 - no/day Top Cased Anchors, 15m long- 1.0 - no/day Anchors stressing- 2.2 - no/day
Bored PilingTask / DescriptionSlow Ave Fast Units Cycle Time, 5-20m deep8.0 4.0 4.0 days/no Cycle Time, 20-40m deep10.0 8.0 - days/no Cycle Time, 40-70m deep25.0 10.0 - days/no Cycle Time, 70-90m deep45.0 25.0 - days/no Cycle Time, 90-135m...
How to format the critical bar? For example, like bellow, the size of the critical bar is thinner than the early bar. [[wysiwyg_imageupload:591:]]
Hello All, I'm having trouble understanding resourcing/resource assignments. Every which way I turn I can't seem to find a place to manually enter a cost per period of an activity. I don't want to base it on a rate, and so enter man-hours to multip...
Hi, Anyone have a copy of all construction trades with task? How about productivity of all trades??? Regards,
Guys' I need some help please! When I installed P6 on my laptop at the first time, everything were installed succesfully including the SQL 2005 server. However when the system is in the process of configuring its databases, PMDB & MMDB, it failed to ...
Dear Members, I am been recently given a job to create a Operations and Maintenance programme for an Offshore facility, which includes Pipeline O & M, Process & Production Platform O & M, Single Point Mooring (SPM) O & M and along with the same its r...
I have a plan which is loaded with man hours, however I can only fit a certain number of men on board the vessel so I want to show a limit on the number of hours in any one day. Can anyone tell me how to set a limit. I know you can do this on eac...
Hello, About to the test the Hot Fix 2 for Primavera 6.7 SP3 and was wondering if anyone has experienced any issue since applying this upgrade patch? Thanks,Stuart
I need to export resource units data from P6 into excel on up to 200 managed projects, and then need to re-import this modified resource/units data back to P6 v6.1 from Excel, once project managers have updated it. The import facility available to s...
Are you staying in Western / Central Africa, and looking for a comprehensive training about MS Project, but not willing to travel to Europe for that?Are you unable to get a training in Europe because of visa restrictions?Enroll in the next session or...
Hi,I would like to cost load the schedule. I do not want to cost load it based on units/time. I want to give an activity a Lump Sum Budgeted Cost. Get a cost curve to see how much we would be spending per month.I have created a Non-labor Resource cal...
Please explain to me am i right or wrong:Base line Program:This term is clear for all. Recovery program:Shall be by taking the last update till known cutoff date and, modify the rest of not started and in progress activities in order to recover the d...
To all co-Planners,I have an unexpeted encounter probs:Facts:I am using P6.1 stand alone.Resource loaded and cost loaded (manpower in 0 price/unit and cost in lump sum 1 price/unit).Using the project as base line.Duration type: Fixed duration and uni...
Hello All,I have Prepared a schedule in P6 and after making initial schedule and Assigning cost to all activities (No Resource Loading Required for the project,only activity cost from BOQ),I saved the Schedule as Primry Baseline.Now When I update the...
Planners;If the project is devided on two sections,section 1--> finish milestone 1section 2--> finish milestone 2(finish milestone 1) greather than (finish milestone 2)Actualy the TF of FM2 =Finish(FM1)-Finish(FM2)I there any way to show critical pat...
What is the difference between Re-forecast and Re-baseline? What should be the criteria of defining bothterms?
We have a number of projects which are update once a week re scheduled and levelled and for months applied Constraint dates have been honored but in the last few weeks these constriants are not working unless they are Mandatory Constraints. I suspec...
I'm looking for some information as to what an independent activty actually is and how it is used. What I've found to date is some info that relates to software programing but actually feel that it may deal with risk within a project. I'm open for ...
Dears,I have question about generating the actual curve in p3, when i update my schedule to a specific data date and generate resource tabular report i get tow different information regarding the actual quantities for resource loading one for early ...