Broken Bars in Bar Chart

A
AB Timo 👤 Member for 15 years

Hello All,

I have Prepared a schedule in P6 and after making initial schedule and Assigning cost to all activities (No Resource Loading Required for the project,only activity cost from BOQ),I saved the Schedule as Primry Baseline.Now When I update the Schedule the Bars before and after the Data date Line are broken.

This Problem is not occuring in Duration % Complete type.Can anyone tell me the reason?

A
AB Timo 👤 Member for 15 years

but in duration % complete it is not the case.only in case of physical % complete.

J
Jash Sales 👤 Member for 16 years 6 months

One reason of activity bar was broken is due to out of sequence realationship with its predecessor. Eventhough your activity is in progress if its driving predecessor is not yet completed or meet their relationship, still the predecessor will push your current bar and it will only start again once your predecessor is completed; thus, made the bar broken.

Forum Sponsor

Top Posters

Trian Asmoro
1 posts
Soheil Barekat
4 posts
Erkan Polater
9 posts
Luis Jr Ngade
6 posts
Ben Welsher
1 posts
Rohan Dashputre
0 posts
AMECHI ANAKWENZE
2 posts
Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts