I have Prepared a schedule in P6 and after making initial schedule and Assigning cost to all activities (No Resource Loading Required for the project,only activity cost from BOQ),I saved the Schedule as Primry Baseline.Now When I update the Schedule the Bars before and after the Data date Line are broken.
This Problem is not occuring in Duration % Complete type.Can anyone tell me the reason?
but in duration % complete it is not the case.only in case of physical % complete.
One reason of activity bar was broken is due to out of sequence realationship with its predecessor. Eventhough your activity is in progress if its driving predecessor is not yet completed or meet their relationship, still the predecessor will push your current bar and it will only start again once your predecessor is completed; thus, made the bar broken.