Dears,
I have question about generating the actual curve in p3, when i update my schedule to a specific data date and generate resource tabular report i get tow different information regarding the actual quantities for resource loading one for early dates and one for late dates so i have tow different actual curve, why this problem appears and how i can solve it
Sorry for my bad language
Regards
Before DD Early and Late S curves are equal to actual as Early Dates and Late Dates are set equal to to Actual Dates. After DD they are different unless all remaining work contributing to the S values are critical.
Plan = Remaining Work after DD