To all co-Planners,
I have an unexpeted encounter probs:
Facts:
I am using P6.1 stand alone.
Resource loaded and cost loaded (manpower in 0 price/unit and cost in lump sum 1 price/unit).
Using the project as base line.
Duration type: Fixed duration and units
Complete % type: Duration
Problem:
When i update, activity with 100% complete will give the earned value as 100%.. But for activity with less 100% complete will give any no performance% complete which means that there is no earned value.
Hope that you can give me hands on this one.. thanks..