Search

(Ask) XERFileParserBuilder

Forum Topic

Does anyone has latest XERFileParserBuilder.xls for 64 bit Windows?I have tried looking for it in the PP forum, but it didn't work.

Jul 17, 2020

Slipped dates reset to baseline after "update progress"

Forum Topic

Hello All,I am a fairly new user to Primavera P6, I am running a couple of schedules by using start dates and duration. Percentage complete is set to physical as the time passed on a task doesn't always reflect the amount of work completed.  There is...

Jul 23, 2020

Export XER file with only some activities

Forum Topic

Dear all,  I want to export an XER file with only some activities not all of them (i want to use it in schedule analyzer after) any help? Thanks!Lyna

Jul 26, 2020

XER Viewers and Schedule Updates

Forum Topic

Hi Folks,Has anyone made use of XER viewers to provide the broader project team with more access to schedule details than would be generally practical with, for example, a PDF copy? These details may relate to a variety of dependencies, calendars, re...

Jul 29, 2020

Formatting Column Width of UTID

Forum Topic

Hi, I have aded the Unique Task ID to the spreadsheet section of my programme as I like to be able to talk about activities by number or WBS rather than lines as line numbers can change dependant on what bars are rolled up in summaries when you print...

Jul 29, 2020

Create Value: Map the Value Stream

Blog

“If you can't describe what you are doing as a process, you don't know what you're doing.” W. Edwards DemingOur work and home lives our bounded by standard operating procedures and process—and too many of them stink.  We all have encountered Byzantin...

Jul 30, 2020

Hydrogen Plant Schedule

Forum Topic

Can anybody provide an example of a detail schedule for design, manufacturing, construction and commissioning of a hydrogen plant? Just been assigend to such aproject and have to provide some initial thought uickly. Any help is appreciated. Thanks.

Aug 4, 2020

Activity Codes and hours not rolling up correctly

Forum Topic

Hi All, i have an issue when looking at several projects, when looking at resource hours as a group and sort and grand totals, it adds up the total of each resource correctly for all projects. However when I seekt to do this to roll up hours for all ...

Aug 4, 2020

Material Resource - Applying an additional fixed cost

Forum Topic

Hi All,I'm in the process of building a fully resource loaded schedule and have recently been advised that I need to apply a 6% internal inventory charge to all materials to recoup internal stores costs.The obvious answer is to adjust the price / uni...

Aug 4, 2020

Confidentiality of Project Data When Shared in XER File Format

Blog

Clearly defined tasks and responsibilities must be given to all project participants, in order to ensure the successful completion of the project.Even more so when a project counts a large number of participants, which makes it more demanding and dif...

Jun 12, 2019

Automated Schedule and Progress Updating

Forum Topic

I am looking for Experts or Academic researchers worked in "Automated Schedule and Progress Updating on 4D BIM" in the UK  to help me with my project in London Business School.ThanksTolga

Jun 13, 2019

P6 Programme Update Issue

Forum Topic

Hi All,I have a latest programme update (monthly) in hand with project completion in June. It is anticipated that extension of time of 3 months to the project would be expected, but due to administration process its unlikely to be awarded anytime soo...

Jun 14, 2019

Importing a previous schedule as the baseline

Forum Topic

Hi Everyone, Is there anyway you can import a previous version of the schedule as a baseline to the current version? I have a subcontractor who updated the schedule and set the baseline on the current dates. Unfortunately the delivery date is a month...

Jun 14, 2019

Budgeted Manhours and Budgeted Cost

Forum Topic

Dear Fellows / Seniors,I got estimates from estimation dept. after winning a tender. in which cost is calculated against manhours but the manhours were worst and was not good estimation. so i created manhours based on my experience. In short now, my ...

Jun 17, 2019

Monthly Manpower from Budgeted Units

Forum Topic

Dear All,I make a schedule. Done resource loading. Add labour resource to the each activity.Now I am trying to make monthly manpower histogram.When I open Resource Assignments windows it's showing the budgeted units allocated to my schedule according...

Jun 18, 2019

Budgeted Manhours and Budgeted Cost

Forum Topic

Dear Fellows / Seniors,I got estimates from estimation dept. after winning a tender. in which cost is calculated against manhours but the manhours were worst and was not good estimation. so i created manhours based on my experience. In short now, my ...

Jun 18, 2019