Export XER file with only some activities

Dear all, 

 

I want to export an XER file with only some activities not all of them (i want to use it in schedule analyzer after) any help?

 

Thanks!

Lyna

P
Patrick Mullen 👤 Member for 6 years

Hi Lyna, are you trying to compare the changes between specific sections of the schedule, and ignore other sections? What information are you trying to analyze once you get the schedule into SA?

Z
Zoltan Palffy 👤 Member for 16 years 10 months

copy the project

filter for the activities that you DO NOT WANT now you are left with waht you want 

press deleted

file export xer 

remember you can not schedule THIS project as there may be ties to activites that have been deleted

D
David Kelly 👤 Member for 21 years 7 months

You need to copy/paste what you want into a new project, and export that. You can ponly export whole projects

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts