Budgeted Manhours and Budgeted Cost

Dear Fellows / Seniors,

I got estimates from estimation dept. after winning a tender. in which cost is calculated against manhours but the manhours were worst and was not good estimation. so i created manhours based on my experience. In short now, my manhours for each activities containing more than one Labor & Equipment resources in one activity are different. Now when i put Price/Unit in Resource Tab of Primavera, i am getting getting different result which is obvious. Now what i want is to reflect Budgeted Cost for each activity same like in the Rates we Quoted to Client using My Manhours. I tried to make a user defined column as Percentage which could multiply the Budgeted Cost to give me the required result but failed.

1111111111.jpg

I successful in Excel but dont know how to do it In Primavera P6. Formula in my Thought to get the required result:

Budgeted Units * Price/Unit * User Defined (%) = BOQ Amount.

 

How to do it? or any Other way??

 

Regards

Bilal

Z
Zoltan Palffy 👤 Member for 16 years 11 months

if you have the Budgeted units and the rates and you make sure that calculate costs from uints thne the budgeted cost will automatically calculate

Forum Sponsor

Top Posters

AMECHI ANAKWENZE
2 posts
Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts
Vahidazimi01
0 posts
David Smith
4 posts
Peter Holroyd
51 posts
fridau
0 posts
Rahmat Hidayat
32 posts
pinoyplanner
1 posts