Importing a previous schedule as the baseline

E
Emma Lang 👤 Member for 9 years 11 months

Hi Everyone, 

Is there anyway you can import a previous version of the schedule as a baseline to the current version? I have a subcontractor who updated the schedule and set the baseline on the current dates. Unfortunately the delivery date is a month later than the contractual date, but the previous baseline detail is now lost. However I do have the original version of the schedule so if there was anyway that information could be imported it would be much easier than taking the activities back to the original state, baselining and replanning. 

 

Any suggestions would be appreciated.

Thanks

E
Evgeny Z. 👤 Member for 18 years 6 months

Emma,

this is not easy, you will need to write some VBA (visual Basic for Applications) code. 

Alternatively you can  use built it feature to compare projects Report=>Compare Projects. This will not make one file to be a baseline, but it will give somewhat comparable functionality

Featured Partner

Top Posters

Zine Eddine
2 posts
Alex Lyaschenko
27 posts
mxsiegel
0 posts
Mattvtek
0 posts
Gareth Evans
3 posts
PP Admin
3, 129 posts
Rajkamal Tangirala
5 posts
Rahul Kumar
1 posts
blake333_
0 posts
Jeamiell Ostrovsky
2 posts