Performance % Complete
Forum TopicI've created a new project in P6 Version 20, and the performance % complete doesn't match the activity % complete. Is there a setting I need to change to make sure these two columns show the same data? thanks
I've created a new project in P6 Version 20, and the performance % complete doesn't match the activity % complete. Is there a setting I need to change to make sure these two columns show the same data? thanks
Concurrent delay: if an owner delays a job for 4 months, can you simply subtract all contractor delays during that time?
Concurrent delay: if an owner delays a job for 4 months, can you simply subtract all contractor delays during that time?
No variance column to compare in Current File Actual finish to Baseline finish - isn't that the most important item? - Am I wrong, I could in P3, it seems crazy that P3 was/is better in many ways....
Concurrent Delay: muti shipment materials, what if the start was delay 30 days in the start, most shipments came in as needed first 50 days AS NEEDED for 100 days of construction, then the last shipments were delayed 20 days (due to failed qa/qc test...
Best import and export selection options - how to keep it the way the client has it without adding your codes to their project?
Helo All,What error am I doing. The below pic shows the duration of the activity and WBS WBS Total570PrimaveraStart Finish Activity A13-Apr-2329-May-2330Activity B30-May-232-Aug-242954Activity C3-Aug-2416-Sep-2445 But the same thing if I put it in e...
Does a contractor get a delay at the beginning of the job added to the end no matter what? What if there is a 20 day access to site owner delay, then later a 40 day contractor delay, but the job ends 21 days late. The contractor made up 40 days. W...
Aren't "windows" delay analysis flawed by the common condensing of schedule as schedule goes on? - Do if the project is complete and you have 5 delays at 20 days each, but he job is only 20 days late - couldn't you just prorate each delay - because...
I have read that you only get time for time that only the owner delayed the project, how can this be - because that would be compensatable. So time extensions are not granted for perfectly equal delays by owner and contractor? For example, I found ...
HiThe first client xer programme that I import into a fresh standalone database will include the activity code assignments. However, when I import further updated xer files, the activity code assignments are not imported.Would be grateful if anyone i...
Can you delineate delays if an item like "special fire wall" are coming 2 months after the project is complete? I assume you can call the item above for "fairness" - if not there is no way around it being the "critical path" / "longest path" - at lea...
Delay Calendar Days vs Effect Calendar Days (delays days less important & which methods discussed Effect Days) Just because a procurement took 246 days to arrive doesn't mean it effected the project 246 Calendar Days. Is there an RP format to show t...
Days Due vs Days needed - what if you when you add up delays each month it is way more than needed? - So do you have to give an extension for way more days than necessary just because there was fat in schedule, or they are able to condense the work...
how do you turn the P6 "enter bell" off? that noise that occurs everytime you type anything..(I normally just turn my system volume off but sometimes I have to listen to something as well working...) - this might be the most important question ever p...
Owner looked at schedule and asked why there were late dates on items with Actuals - what do you say? what do you do? - because it is true, it does not make sense. I assume people copy the dates to a column and delete them in the udf column - but so...
Vladimir, I am looking for a way to do update all material and resources costs on a weekly basis. Here is what I am thinking: 01. Use a database (doesn't matter wich one) as long as it can export a simple text file. The database will store codes of m...
We know that dates are often off by 1 day because there are hidden decimals - but main source & main fix?
Traditional views tend to favour a management approach built on the assumption that more detail is better—and to a point, this is undoubtedly correct. Insufficient detail in a plan of any type is a sure way to fail. But, there’s no right answer to t...
Hi AllAnyone who is conversant with CCDC 2 (Canadian Construction Contracts) should be able to help me out. QuestionI am looking for an equivalent of FIDIC Clause 52.3 (Variation Exceeding 15%) in CCDC 2 FIDIC Clause 52.3allows the Contractor and Eng...