No variance column to compare in Current File Actual finish to Baseline finish - isn't that the most important item? - Am I wrong, I could in P3, it seems crazy that P3 was/is better in many ways....
No variance column to compare in Current File Actual finish to Baseline finish - isn't that the most important item?
Forum Sponsor
Top Posters
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts
Rodel has the answer
Variance Column is always available in P6. It's under Duration group. See below: