Does a contractor get a delay at the beginning of the job added to the end no matter what?

Does a contractor get a delay at the beginning of the job added to the end no matter what?  What if there is a 20 day access to site owner delay, then later a 40 day contractor delay, but the job ends 21 days late.  The contractor made up 40 days.  Who is the delay on?  Does it matter which is first?